H2 2. Lead time that you can plan against
Lead time is not a number; it is a sum of actions:
- Sample approval: 3–7 days on stock sizes
- New tooling: 15–25 days, excluding mold revision
- Mass production: 20–30 days
- Printing and finishing: 3–8 days, stacked by process count
- Packing and customs: 3–5 days
- Ocean freight: 20–40 days by route
Write "sample approval date" into the contract as the single starting point, not "order date." That removes the ambiguity both sides otherwise argue about.
Peak season (August to October) tightens capacity — book two to three weeks earlier.
OEM/ODM Airless Bottle projects also need joint validation time for structure and pump, a step clients rarely budget for.
H2 3. Five things to inspect
One, vacuum hold. Build negative pressure, hold, and watch for recovery — the only effective test of piston sealing.
Two, pump output. Ten consecutive strokes, measured against the stated range.
Three, print adhesion. 3M tape pull, measuring the area of ink removal.
Four, color consistency. Compare against a chip under a standard light box; dark parts must always be compared.
Five, fit and packing. Overcap snap force, pump torque, packed quantity, carton weight.
H2 4. Clauses worth writing into a PO
- Acceptance: state AQL level and color-difference range, with a chip reference number
- Residual ceiling: essential for viscous products, especially Airless Cosmetic Cream Bottle formats
- Packing method: bodies, pumps and overcaps packed separately, with a packing list
- Breakage liability: define who owns loss under FOB versus CIF
- Replenishment: agree the ratio and turnaround for out-of-tolerance color or functional failure
H2 5. Three questions to ask at inspection
Ask which pump lot this is — mixing pump lots is a frequent cause of failure. Ask for the color chip number — "deep blue" verbally means nothing. Ask for carton gross weight — cartons over 20kg attract surcharges at overseas warehouses.